DPW000229462
Report Public Right of Way Concern
Public Works
- Requested
- March 11, 2026
- Subtype
- Construction equipment blocking right of way
- Location
- Grayland Ave & S Arthur Ashe Blvd N
- As reported by the submitter and published by the City. May be the submitter’s address or another party’s; the City does not anonymize to block level.
- Council District
- 5
- Neighborhood
- The Fan
Description
Citizen is reporting between Grayland Ave and N. Arthur Ashe a construction company blocked of the road. There is no traffic control on Grayland and the company advised that it was a temporary issue and no permits were needed.
Details
- Is Vehicle Traffic Blocked?
- Yes -street is blocked
- Is Pedestrian Traffic Blocked?
- Yes - sidewalk is blocked
- Is a Permit Visible?
- No Permit Visible
History
- March 11, 2026The service request is submitted.
- March 11, 2026The service request status has been changed to Assigned to Department.
- March 11, 2026The service request status has been changed to Assigned to Engineer.
- March 11, 2026The service request status has been changed to In Progress.
- March 12, 2026The service request status has been changed to Completed.
Comments
- Staff · March 12, 2026The Department of Public Works conducted a field inspection of the location following your report. At the time of the inspection, no construction activity was observed within the public right-of-way and no obstructions to the roadway or sidewalk were present. The area appeared to be open and accessible, and no conditions requiring traffic control or permitting were identified. Based on the inspection findings, no violation of the City’s right-of-way regulations was observed at this location at this time. However, we appreciate you notifying us of the situation, as citizen reports help us ensure that work occurring within the public right-of-way is properly permitted and conducted safely.