Beta release. We are still refining and welcome feedback.

DPW000086985

Repair Road

Public Works

How we assembled this data →

CompletedClosed February 9, 2023
Requested
August 19, 2021
Subtype
Street Pavement Repair
Location
800 N 35th St, 23223
As reported by the submitter and published by the City. May be the submitter’s address or another party’s; the City does not anonymize to block level.
Council District
7
Neighborhood
Chimborazo

Description

Caller states two months ag o the fire hydrant was dug up to replace pipes. Gravel was packed in hole and caller was informed there would topsoil placed and as a result of the backhoe, a large pothole in the the street with mud. A large amount of gravel was placed in the alley and caller would like to know the gravel will be removed from behind her home and a ton of gravel was left in alley. 35th and N Street; caller would like to know why the same surface is not in 800 Block as the 700 Block

History

  1. August 19, 2021
    The service request is submitted.
  2. August 19, 2021
    The service request status has been changed to Assigned to Department.
  3. August 19, 2021
    The Reporter logged a follow-up request from a constituent.
  4. February 9, 2023
    The service request status has been changed to Completed.

Comments

  • Staff · August 19, 2021
    Cityworks ID: 452205
  • System · August 19, 2021
    Caller states she is having a problem pulling out trash can because of all he gravel. Street was paved last year, the backhoe has created a large and it was showed to contractors when they was performing the work.
  • Staff · February 9, 2023
    omplete per D. Carter's inspection.