Beta release. We are still refining and welcome feedback.

DPW000071515

Repair Road

How we assembled this data →

CompletedClosed August 17, 2021
Requested
February 11, 2021
Subtype
Street Pavement Repair
Location
324 Libbie Ave, 23226
As reported by the submitter and published by the City. May be the submitter’s address or another party’s; the City does not anonymize to block level.
Council District
1
Neighborhood
Three Chopt

Description

There are two locations at this intersection, both on Libbie, that were excavated last year. The initial repairs were poor, and resulted in uneven pavement. Both have been repaved, however, they are still not flush with the existing pavement. Furthermore, as I understand the City of Richmond Excavation Restoration Manual, the asphalt should be replaced from curb to curb, not just the area that was dug up, since that section had been newly paved within 6 months of the disturbance. This request is going on six months, with no apparent resolution. As of this weekend, an orange and white traffic barrel has been placed over one spot of the two patches that had become an actual pot hole. When is the repaving, from curb to curb going to be done?

History

  1. February 12, 2021
    The service request is submitted.
  2. February 12, 2021
    The service request status has been changed to Assigned to Department.
  3. August 17, 2021
    The service request status has been changed to Completed.

Comments

  • Staff · February 12, 2021
    Cityworks ID: 437826
  • Staff · August 17, 2021
    Per W.D complete 8-16-21
  • Staff · August 17, 2021
    Per W.D complete 8-16-21
  • Staff · August 17, 2021
    Problem Description: There are two locations at this intersection, both on Libbie, that were excavated last year. The initial repairs were poor, and resulted in uneven pavement. Both have been repaved,however, they are still not flush with the existing pavement. Furthermore, as I understand the City of Richmond Excavation Restoration Manual, the asphalt should be replaced from curb to curb, not just the area that was dug up, since that section had been newly paved within 6 months of the disturbance.;

Spotted a problem with this record?