Storm drains at corner of 2400 block of Rosewood Ave and S Davis back up after every storm from minutes to a day
Details
- Is the inlet/basin clogged?
- Yes
- Is the street flooding?
- Yes
- Is there an odor coming from the basin?
- Yes
History
- August 1, 2022The service request is submitted.
- August 1, 2022The service request status has been changed to Assigned to Department.
- January 19, 2023The service request status has been changed to Completed.
Comments
- Staff · August 1, 2022Cityworks ID: 478402
- Staff · August 1, 2022Request will be relay to Field Supervisor for assessment please allow time 15 days for Supervisor to complete assessment. Supervisor will contact requester upon completion of assessment.
- Staff · August 26, 2022N.Sumpter,S.Crews and C.JordanThis location had 2 of 2 that were inspected for clean and service, 2 of 2 needs service and is marked. Sediment and Debris.
- Staff · January 19, 2023DPU Stormwater contractors PipeVision are assigned to this location and have as a prevented maintained routine, the crew clean location with high water and a vacuum truck. Crew clean sub and basin with a high-pressure hose and high-pressure vacuum.