DPU000018613

Clean Stormwater Drain

Public Utilities

How we assembled this data →

CompletedClosed April 11, 2022
Requested
March 23, 2022
Subtype
Basin Cleaning
Location
N 26th St & E Leigh St
As reported by the submitter and published by the City. May be the submitter’s address or another party’s; the City does not anonymize to block level.
Council District
7
Neighborhood
Church Hill

Description

The request is to have several inlets cleaned at this intersection due to blockages of leaves and debris. Anal cleanings are needed at 27th and Leigh st, 28th and Leigh and 30th and Leigh.

Details

Is the inlet/basin clogged?
Yes
Is the street flooding?
Yes
Is there an odor coming from the basin?
No

History

  1. March 23, 2022
    The service request is submitted.
  2. March 23, 2022
    The service request status has been changed to Assigned to Department.
  3. April 11, 2022
    The service request status has been changed to Completed.

Comments

  • Staff · March 23, 2022
    Cityworks ID: 467154
  • Staff · March 24, 2022
    Request will be relay to Field Supervisor for assessment please allow time 15 days for Supervisor to complete assessment. Supervisor will contact requester upon completion of assessment.
  • Staff · March 24, 2022
    Locations have been assessed by DPU personnel all need serviced.
  • Staff · April 11, 2022
    S.Crews, W .Mayo and M. Gray(Temp),are assigned to this location have, crew clean location with high water and vacuum truck. Crew clean sub and basin with high pressure hose and high pressure vacuum.