DPU000018090
Clean Stormwater Drain
Public Utilities
- Requested
- February 8, 2022
- Subtype
- Basin Cleaning
- Location
- 711 N Arthur Ashe Blvd, 23220
- As reported by the submitter and published by the City. May be the submitter’s address or another party’s; the City does not anonymize to block level.
- Council District
- 2
- Neighborhood
- The Fan
Description
Water continues to flood the corner of Grace and Arthur Ashe
Details
- Is the inlet/basin clogged?
- Yes
- Is the street flooding?
- Yes
- Is there an odor coming from the basin?
- No
History
- February 8, 2022The service request is submitted.
- February 8, 2022The service request status has been changed to Assigned to Department.
- December 12, 2022The service request status has been changed to Completed.
Comments
- Staff · February 8, 2022Cityworks ID: 464088
- Staff · February 8, 2022Request will be relay to Field Supervisor for assessment please allow time 15 days for Supervisor to complete assessment. Supervisor will contact requester upon completion of assessment.
- Staff · February 8, 2022Request will be relay to Field Supervisor for assessment please allow time 15 days for Supervisor to complete assessment. Supervisor will contact requester upon completion of assessment.
- Staff · February 8, 2022Request will be relay to Field Supervisor for assessment please allow time 15 days for Supervisor to complete assessment. Supervisor will contact requester upon completion of assessment.
- Staff · March 17, 2022L.Lockett , this location had 4 of 4 that were inspected for clean and service. 4 of 4 needs service and is marked. Full of trash and sediment
- Staff · March 17, 2022Also at the corner of this location a cavitation is at the South West corner the location was already safety as cone were place around the basin and the cavitation itself.
- Staff · December 3, 2022T.Johnson ,and C.Jordan This location had 4 of 4 that were inspected for clean and service, 1 of 4 needs service and is marked. Trash and Debris.
- Staff · December 12, 2022DPU Stormwater contractors PipeVision are assigned to this location and have as a prevented maintained routine, the crew clean location with high water and a vacuum truck. Crew clean sub and basin with a high-pressure hose and high-pressure vacuum.