DPU000011004
Clean Stormwater Drain
- Requested
- September 29, 2020
- Subtype
- Basin Cleaning
- Location
- 1600 N 19th St, 23223
- As reported by the submitter and published by the City. May be the submitter’s address or another party’s; the City does not anonymize to block level.
- Council District
- 7
- Neighborhood
- Eastview
Description
Storm drain next to fire hydrant is clogged from street sweeping debris
Details
- Is the inlet/basin clogged?
- Yes
- Is the street flooding?
- No
- Is there an odor coming from the basin?
- No
History
- September 29, 2020The service request is submitted.
- September 29, 2020The service request status has been changed to Assigned to Department.
- March 8, 2021The Reporter logged a follow-up request from a constituent.
- September 24, 2021The service request status has been changed to Completed.
Comments
- Staff · September 29, 2020Cityworks ID: 429510
- Staff · October 6, 2020Request has been received and dispatched to supervisor for investigation. Please allow 15 day for assessment to be completed. Supervisor will contact customer once investigation is complete
- System · October 14, 2020Following us as he has not heard anything about the storm drain. Citizen is eager to get the problem fixed as it's been an ongoing problem. Please reach out to citizen once investigation is complete
- System · October 22, 2020Returned Voicemail. Left message on citizens voice mail. Please refer to notes on 10/06/20 from DPU advising of the next steps related to any cleaning/repairs needed for the basin
- Staff · November 19, 2020M I have contacted the concerned citizen and explained the situation as to the particular inlet he has referred to. We will revisit the location in the week to follow.
- Staff · November 24, 2020M Inlet had been treated for roots.
- System · March 8, 2021Caller phoned back in, states drains on 1600 block of N 19th St have had leaf blockage issues since October of 2020, has photographic evidence & will be complaining directly to DPU at City Hall regarding lack of drain cleaning
- Staff · September 24, 2021M DPU Stormwater contractors PipeVision are assigned to this location have, crew clean location with high water and vacuum truck. Crew clean sub and basin with high ressure hose and high pressure vacuum. The location total inlets were 3 which all inspected 3 of the 3 were cleaned for serviced. Roots,mud and leaves were found. Some roots were removed but was unable to clear the pipe.