Beta release. We are still refining and welcome feedback.

DPU000010117

Clean Stormwater Drain

How we assembled this data →

CompletedClosed February 5, 2021
Requested
August 11, 2020
Subtype
Basin Cleaning
Location
401 Hunt Ave, 23222
As reported by the submitter and published by the City. May be the submitter’s address or another party’s; the City does not anonymize to block level.
Council District
3
Neighborhood
Providence Park

Description

basin cleaning at woodson ave

Details

Is the inlet/basin clogged?
Yes
Is the street flooding?
Yes
Is there an odor coming from the basin?
Yes

History

  1. August 11, 2020
    The service request is submitted.
  2. August 11, 2020
    The service request status has been changed to Assigned to Department.
  3. August 25, 2020
    The Reporter logged a follow-up request from a constituent.
  4. February 5, 2021
    The service request status has been changed to Completed.

Comments

  • Staff · August 11, 2020
    Cityworks ID: 425244
  • Staff · August 11, 2020
    Request has been received and dispatched to supervisor for investigation, Please allow 15 days for investigation. Supervisor will contact customer once investigation is complete
  • System · August 25, 2020
    Citizen called in for an update
  • System · August 31, 2020
    Caller states she called about the gutters needing to be cleaned and she states to date it hasn't been done; caller was advised that an email can be sent to the Stormwater division advising that the status is needed being that it's been about the 15 days for the investigation. Caller states no she would rather have the number to the Mayor's office.
  • System · August 31, 2020
    Mayor escalation - called back to check on status and also to advise that the basin in front of 329 Hunt ave needs to be cleaned (both sides of the intersection of Woodson and Hunt
  • Staff · January 14, 2021
    . Request will be relay to Field Supervisor for assessment please allow time 15 days for Supervisor to complete assessment. Supervisor will contact requester upon completion of assessment.
  • Staff · January 14, 2021
    . Request will be relay to Field Supervisor for assessment please allow time 15 days for Supervisor to complete assessment. Supervisor will contact requester upon completion of assessment.
  • Staff · February 5, 2021
    completed 1/27/2021..DPU Stormwater contractors PipeVision assigned to this location, cleaned location with high water and vacuum truck. Crew clean sub and basin with high pressure hose and high pressure vacuum. inspected, serviced and cleaned total 6 inletsof trash, large concrete curb pieces

Spotted a problem with this record?