DPU000009722
Clean Stormwater Drain
- Requested
- July 13, 2020
- Subtype
- Basin Cleaning
- Location
- 2017 Lamb Ave, 23222
- As reported by the submitter and published by the City. May be the submitter’s address or another party’s; the City does not anonymize to block level.
- Council District
- 6
- Neighborhood
- Southern Barton Heights
Description
Completely filled with trash
Details
- Is the inlet/basin clogged?
- Yes
- Is the street flooding?
- Yes
- Is there an odor coming from the basin?
- Yes
History
- July 13, 2020The service request is submitted.
- July 13, 2020The service request status has been changed to Assigned to Department.
- March 18, 2021The service request status has been changed to Completed.
Comments
- Staff · July 13, 2020Cityworks ID: 422819
- Staff · July 14, 2020
- Staff · July 14, 2020Problem Description: Concrete broken and rebar is exposed and creating hazard.;Is the concrete or brick missing? Concrete missing; Is metal exposed? Yes; Is the top or cover missing? Not missing; Approximate size of the opening? Greater than 12 inches; Is the problem in the rear of the property? No; Is the problem in the front of the property? Yes; Is the problem on the side of the property? No;
- Staff · July 14, 2020See Ticket CW# 422819 and RVA 311# CRMDPU000009722-. Request will be relay to Field Supervisor for assessment please allow time 15 days for Supervisor to complete assessment. Supervisor will contactrequester upon completion of assessment. Also request will be elevate as the location still has an ongoing issue
- Staff · July 14, 2020Error in entry will not be closed. Until request is completed.
- Staff · July 14, 2020See Ticket CW# 422821 and RVA 311# CRMDPU000009723-. Request will be relay to Field Supervisor for assessment please allow time 15 days for Supervisor to complete assessment. Supervisor will contactrequester upon completion of assessment. Also request will be elevate as the location still has an ongoing issue.
- Staff · March 18, 2021completed 3/4/2021...Per Lockett, DPU Stormwater contractors PipeVision were assigned to this location, crew cleaned location with high water and vacuum truck. Crew cleaned sub and basin with high pressure hose and high pressure vacuum. Cleared 3 inlets of trash, mud and roots. One outflow pipe 100% full of roots.