DPU000009722

Clean Stormwater Drain

How we assembled this data →

CompletedClosed March 18, 2021
Requested
July 13, 2020
Subtype
Basin Cleaning
Location
2017 Lamb Ave, 23222
As reported by the submitter and published by the City. May be the submitter’s address or another party’s; the City does not anonymize to block level.
Council District
6
Neighborhood
Southern Barton Heights

Description

Completely filled with trash

Details

Is the inlet/basin clogged?
Yes
Is the street flooding?
Yes
Is there an odor coming from the basin?
Yes

History

  1. July 13, 2020
    The service request is submitted.
  2. July 13, 2020
    The service request status has been changed to Assigned to Department.
  3. March 18, 2021
    The service request status has been changed to Completed.

Comments

  • Staff · July 13, 2020
    Cityworks ID: 422819
  • Staff · July 14, 2020
  • Staff · July 14, 2020
    Problem Description: Concrete broken and rebar is exposed and creating hazard.;Is the concrete or brick missing? Concrete missing; Is metal exposed? Yes; Is the top or cover missing? Not missing; Approximate size of the opening? Greater than 12 inches; Is the problem in the rear of the property? No; Is the problem in the front of the property? Yes; Is the problem on the side of the property? No;
  • Staff · July 14, 2020
    See Ticket CW# 422819 and RVA 311# CRMDPU000009722-. Request will be relay to Field Supervisor for assessment please allow time 15 days for Supervisor to complete assessment. Supervisor will contactrequester upon completion of assessment. Also request will be elevate as the location still has an ongoing issue
  • Staff · July 14, 2020
    Error in entry will not be closed. Until request is completed.
  • Staff · July 14, 2020
    See Ticket CW# 422821 and RVA 311# CRMDPU000009723-. Request will be relay to Field Supervisor for assessment please allow time 15 days for Supervisor to complete assessment. Supervisor will contactrequester upon completion of assessment. Also request will be elevate as the location still has an ongoing issue.
  • Staff · March 18, 2021
    completed 3/4/2021...Per Lockett, DPU Stormwater contractors PipeVision were assigned to this location, crew cleaned location with high water and vacuum truck. Crew cleaned sub and basin with high pressure hose and high pressure vacuum. Cleared 3 inlets of trash, mud and roots. One outflow pipe 100% full of roots.