Beta release. We are still refining and welcome feedback.

DPU000008580

Clean Stormwater Drain

How we assembled this data →

CompletedClosed November 23, 2021
Requested
March 1, 2020
Subtype
Basin Cleaning
Location
821 Catherine St, 23220
As reported by the submitter and published by the City. May be the submitter’s address or another party’s; the City does not anonymize to block level.
Council District
2
Neighborhood
Carver

Description

This drain is clogged and the street floods in heavy rains

Details

Is the inlet/basin clogged?
Yes
Is the street flooding?
Yes
Is there an odor coming from the basin?
No

History

  1. March 1, 2020
    The service request is submitted.
  2. March 1, 2020
    The service request status has been changed to Assigned to Department.
  3. November 23, 2021
    The service request status has been changed to Completed.

Comments

  • Staff · March 1, 2020
    Cityworks ID: 415475
  • Staff · March 2, 2020
    ervice Request has been received and dispatched to Field Supervisor for assessment. Please allow 15 days for Supervisor to complete assessment. Supervisor will contact requester upon completion of assessment.
  • Staff · March 15, 2021
    inspected and completed on 3/5/2021...Per Lockett...DPU Stormwater contractors PipeVision were assigned to this location, crew cleaned location with high water and vacuum truck. Crew cleaned sub and basin with high pressure hose and high pressure vacuum. Cleared 2 inlets of sand and trash....