DPU000006220
Report Clearing or Erosion Issues on Construction Site
- Requested
- August 6, 2019
- Subtype
- Assess land disturbance or erosion
- Location
- 5404 New Kent Road 23225
- As reported by the submitter and published by the City. May be the submitter’s address or another party’s; the City does not anonymize to block level.
- Council District
- 4
- Neighborhood
- Westover Hills
Description
Dirt from a work site on New Kent Road is going on the road and flooding the road and overwhelming the nearby storm drains.
Details
- Is erosion/sediment from a construction site?
- Yes
- Is water/sediment leaving the construction site?
- Yes
- Does issue involve clearing of trees or vegetation
- Yes
- Is erosion or land clearing on private property?
- Yes
- Is public right of way or city property impacted?
- Yes
- Is erosion/drainage issue affecting your property?
- No
- Is the problem near a stream or the James River?
- Yes
History
- August 6, 2019The service request is submitted.
- August 6, 2019The service request status has been changed to Assigned to Department.
- August 6, 2019The service request status has been changed to Assigned to Engineer.
- August 13, 2019The service request status has been changed to In Progress.
- August 27, 2019The service request status has been changed to Completed.
Comments
- System · August 6, 2019A site inspector will visit the site on Wednesday August 7th, 2019.
- System · August 7, 2019Spoke with Contractor Zach Kennedy and they are in the process of a clean up. We will follow up on Friday,8-9-2019
- Staff · August 15, 2019Contractor was served a notice of violation and will have (7) days to make corrections to the site. A follow up inspection will occur on 8-23-19.
- Staff · August 27, 2019Additional perimeter controls were installed. The grading crew will bring the site to final grade and stabilize the area this week. Inspector will continue to monitor the site to ensure compliance.
- Staff · August 27, 2019Additional perimeter controls were installed. The grading crew will bring the site to final grade and stabilize the area this week. Inspector will continue to monitor the site to ensure compliance.