DPU000005168

Clean Stormwater Drain

How we assembled this data →

CompletedClosed December 12, 2022
Requested
May 14, 2019
Subtype
Basin Cleaning
Location
900 E Broad St
As reported by the submitter and published by the City. May be the submitter’s address or another party’s; the City does not anonymize to block level.
Council District
6
Neighborhood
Capitol District

Description

Southbound end at the bridge where it intersection of commerce and it is in the right lane and the water seems like it is coming sewer lid. If you go to perry street you have gone to far.

Details

Is the inlet/basin clogged?
Yes
Is the street flooding?
Yes
Is there an odor coming from the basin?
No

History

  1. May 14, 2019
    The service request is submitted.
  2. May 14, 2019
    The service request status has been changed to Assigned to Department.
  3. December 12, 2022
    The service request status has been changed to Completed.

Comments

  • Staff · May 14, 2019
    Cityworks ID: 395706
  • Staff · May 28, 2019
    Service request has been received and dispatched. Please allow Field Supervisor 15 days to complete assessment. Field Supervisor will contact requestor upon completion of assessment.
  • Staff · March 15, 2022
    L.Lockett , This location had 1 of 1 that were inspected for clean and service, 1 of 1 needs service and is marked. Trash and Debris. Parking sings are needed at this location so it can be serviced.
  • Staff · April 22, 2022
    No Parking signs are needed at this location
  • Staff · April 22, 2022
    L.Lockett , this location had 3 of 3 that were inspected for clean and service. 3 of 3 needs service and is marked. Sediment and Leaves
  • Staff · May 6, 2022
    DPU Stormwater contractors PipeVision are assigned to this location have, crew clean location with high water and vacuum truck. Crew clean sub and basin with high pressure hose and high pressure vacuum. Location was schedule for service NO parking sign were set up 48 hrs prior to service. Two in row sign were not down or removed and citizen were not complication with the order for no parking because service were going to done on two day period.
  • Staff · December 12, 2022
    DPU Stormwater contractors PipeVision are assigned to this location and have as a prevented maintained routine, the crew clean location with high water and a vacuum truck. Crew clean sub and basin with a high-pressure hose and high-pressure vacuum.