DPU000002406

Assess Standing Water

How we assembled this data →

CompletedClosed March 10, 2020
Requested
October 25, 2018
Subtype
Assess Stormwater
Location
4000 Traylor Dr 23235
As reported by the submitter and published by the City. May be the submitter’s address or another party’s; the City does not anonymize to block level.
Council District
4
Neighborhood
Huguenot

Description

rt running underneath the street parallel to Apache perpendicular to trailer driver there is gravel and ll kinds of debris covert has rotted away and rusty and may need to replace the pipe

Details

Problem area
Street
Is there standing water?
No
Is the problem in the rear of the property?
No
Is the problem in the front of the property?
No
Is the problem on the side of the property?
Yes
Is there a erosion issue?
Yes
Is the problem in the creek or stream?
No
Is this related to vegetation?
No

History

  1. October 25, 2018
    The service request is submitted.
  2. October 25, 2018
    The service request status has been changed to Assigned to Department.
  3. December 16, 2019
    The Reporter logged a follow-up request from a constituent.
  4. February 18, 2020
    The Reporter logged a follow-up request from a constituent.
  5. March 10, 2020
    The service request status has been changed to Completed.

Comments

  • Staff · October 25, 2018
    Cityworks ID: 380559
  • Staff · September 21, 2019
    Refer to CW # 378768.
  • System · December 16, 2019
    Calling to check on request; culvert is getting worse
  • System · February 18, 2020
    check the status of request
  • System · February 18, 2020
    the situation has gotten worse need a called back with a plan of action
  • System · February 18, 2020
    Email sent to DPU as citizen escalation regarding issue
  • Staff · March 9, 2020
    lease allow 15 days for Supervisor to complete assessment. Supervisor will contact requester upon completion of assessment.
  • Staff · March 10, 2020
    Per. W.Tolson Field Supervisor stated that his crew did ditch maintained and pipe replacement on 3/9/2020.